Financing Approval

Due February 12, 2021

First Selections Meeting

February 11, 2021

Exterior Selections:

  • Confirm windows/doors

  • Roofing options

  • Siding options

  • Soffit/fascia/eavestrough options

  • Decking options

  • Parging options

10% Deposit Due

Received

Second Selections Meeting

February 25, 2021 - 4:30pm

Confirm any outstanding exterior selection choices

Interior Selections:

  • Fireplace

  • Flooring

  • Shiplap

  • Lighting

  • Paint Colours

  • Millwork?

Final Selections Meeting

Week of March 8-12, 2021

Confirm any outstanding selection choices

Construction Kickoff

As soon as possible in spring

40% Draw

Due at substantial completion of framing

Approximately end of May

Addition Completion
Final 50% Due

Approximately end-June to end-July, depending on spring weather conditions

BE IN 
TOUCH

126 Maple St., Morden, MB, Canada R6M 1H4

James Francis 204-823-0929; james.ffh@gmail.com

Heather Francis 204-823-0725; heather.ffh@gmail.com

© 2018 by Francis Family Homes

  • White Facebook Icon
  • Instagram